In connection with completed commissioning of infrastructure related to the Vertical Gas Corridor project, the technical capacity for natural gas transmission from Bulgaria to Romania, at IP Negru Voda 1 (RO)/ Kardam (BG) (exit) (21Z000000000159I), will increase to 296 796 409 kWh/day, effective from 17 November 2026. The relevant available capacity products will be offered in accordance with the ENTSOG auction calendar as of 16 November 2026.

DETAILS ABOUT THE EVENT ARE PUBLISHED ON ENETSOG TP *

 *According to Article 4(1) and Article 4a of REMIT II (Regulation (EU) 2024/1106 amending regulations (EU) № 1227/2011 and (EU) 2019/942), market participants shall disclose the inside information through inside information platforms authorized by ACER.